Pike will pave Railroad Avenue and Water Street from the parking lot to Lincoln Street, complete street paving work for Water Street and all side streets; and excavate and gravel the sidewalk area from Mammy's Bakery to Fort Hill Street. Maineway Landscaping & Excavation is set to complete repair of the granite steps and repointing of the cobblestone walls, and begin placing bricks for sidewalk areas.
Moulison Heavy Electrical is set to complete installing and wiring of traffic signal and highway lighting structures. This is expected to take three to four weeks.
Moulison Heavy Electrical is set to complete installing and wiring of traffic signal and highway lighting structures. This is expected to take three to four weeks.