MDOT downtown project update

Tue, 10/09/2018 - 3:00pm

The fence at the Haggett Building will be removed this week. Jersey barriers will be placed in the Haggett Building parking lot and signs will be installed. Test drilling will be done on Route 1 for the mast arm foundations and the light bases. Railroad and Water streets will be striped, and the shim and curb in that area will be paved. Drainage will be installed on Route 1.

The week of Oct. 15, installation of signs on Railroad Avenue and Water Street will continue. Lighted bollards will be placed on Railroad Avenue, and drainage work on Route 1 will be ongoing.